Task 1: (Verbal progress report for the project) 3 minutes per group
- One member from each group presents the progress of their group
- Use 1-2 slides
- Introduce their group members and their roles.
- Report on progress and plans for the remaining of the project.
Task 2:
Create a precedence activity network using the following details. You can draw this on paper or use a tool of your choice.
Activity | Depends on | Duration(days) |
A | 5 | |
B | A | 7 |
C | B | 6 |
D | A | 5 |
E | D | 10 |
F | B | 15 |
G | B | 8 |
H | G | 8 |
I | C | 4 |
J | G | 4 |
K | E,F | 5 |
L | I,H | 3 |
Calculate the earliest and latest start and end dates and the float associated with each activity. From this identify the critical path.